Reconstruction of Enashiminskaya HPP has been completed

Main/News

 

In September and October this year, GES-engineering LLC performed disassembly, assembly, and commissioning as part of the reconstruction of the main water intake facility at the Yenashiminskaya Hydro Power Plant (HPP).
This was the final stage of reconstruction of the automation, alarm and excitation system for hydro generators No. 1-4 and the hydraulic engineering measurement system at the head station and the main water intake facility, including the plant's automated process control system. The reconstruction started in April 2014.
GES-engineering LLC and the Yenashiminskaya HPP will continue to cooperate. The companies are going to conclude a service agreement for the system and the plant equipment.

 

 Note:
GES-Engineering LLC is a subsidiary of LLC “EuroSibEnergo Engineering Company”, which is a part of the largest independent power company in Russia EuroSibEnergo (owned by En+Group).

Date of addition: 28.10.2016